Here's a complete engineering assessment as a standalone HTML page you can drop straight into your website. It quantifies the joint demands, sizes the required frame, compares cable vs. no-cable versions, and gives a clear verdict with supporting math. ```html
Trimaran-wing seastead · 44 ft equilateral frame · NACA 0035 legs · joint stress analysis, frame sizing, and cable vs. no-cable trade study
The 8.5-ft-chord foil legs have enormous bending stiffness. Even the worst credible storm and accidental loads stress the leg shell to under ~11 ksi against a 65 ksi yield — a margin of 6× or more.
The leg shell is never the weak link. The design effort belongs in the corner node castings/fabrications and the slip-critical bolted flange. Both are conventional, well-understood steelwork.
Cables would add stiffness and redundancy but are not needed for strength. They add ~$2–12k capex, ongoing tensioning/inspection, and possible strum noise. Go cable-free; weld in retrofit lugs as insurance.
You specified the geometry precisely; the environmental criteria were not specified, so the following design environment was assumed. If your survival criterion is harsher (e.g., open-ocean hurricane), the loads scale roughly with the square of velocity and must be rerun — see §11.
| Parameter | Value used | Source |
|---|---|---|
| Displacement Δ | 27,500 lb (854 slugs) | Your rating |
| Seawater density γ | 64 pcf | Standard |
| Leg foil | NACA 0035, chord 8.5 ft, max thickness 2.98 ft, span 21.5 ft, height 14.5 ft (7.25 ft draft) | Your spec |
| Foil section area | ≈ 17.2 ft² (0.68 × t × c) | Computed |
| Leg shell skin | 3/16 in duplex, internal frames @ 12–18 in | Assumed (see §5) |
| Operating environment | 15 kt wind, 3-ft seas, 5 kt cruise | Assumed |
| Survival environment (parked on tethers) | 70 kt gusting wind, Hs = 15 ft, T ≈ 9–11 s | Assumed |
| Tension-leg pull-down | 3 ft → +9.9 kip buoyancy, ≈ 3.3 kip static tension per tether | Your spec |
| Allowable stresses | 30 ksi extreme (≈ 0.46 σy); weld details checked for fatigue separately | Practice |
| Bolts | Duplex A4-90, 1″ dia., slip-critical (Class B faying, μ ≈ 0.45–0.5) | Assumed |
| Item | Value | Note |
|---|---|---|
| Submerged volume per leg (17.2 ft² × 7.25 ft) | 125 ft³ | ≈ 7,980 lb per leg |
| Three legs, bare foil | 23,940 lb | — |
| + heave plates, conduit, thruster pods, appendages | +3,560 lb | Scales to your 27,500 lb rating ✓ |
| Waterplane area (3 foils) | ≈ 52 ft² | 3,300 lb per ft of level change |
| Buoyancy change per 1 ft of water level | 12% of Δ | You quoted 1/7 (14%) — you're in the right range; heave-plate edges close the gap |
| Static buoyancy share per leg | 9.2 kip | 27,500 ÷ 3 |
Building up the full weight from component estimates, the design comes out heavy against the 27,500 lb rating. This is independent of the cable question, but you should see it:
| Group | Est. weight (lb) |
|---|---|
| Legs (3 × ~2,300: shell, frames, 4 airtight bulkheads, flange, ladder, conduit) | 6,900 |
| Frame, walls, floor, ceiling, corner nodes | 9,800 |
| Walkway, railing, ladders (aluminum) | 1,400 |
| Heave plates, thruster mounts, conduit | 1,100 |
| 6 rim-driven thrusters | 700 |
| Batteries (25% of Δ, LFP ≈ 340 kWh) | 6,875 |
| Solar array + racks + charge controllers | 900 |
| Wiring, plumbing, electronics | 1,100 |
| Interior fitout (berths, galley, head) | 1,600 |
| Dinghy + HARMO outboard | 700 |
| Safety gear, misc. | 500 |
| Total estimate | ≈ 31,600 |
| Your rating | 27,500 |
| Gap | ≈ −4,100 |
All demands below are per leg, at the top joint (the flange plane at +7.25 ft, i.e., the underside of the floor). "Shear" is horizontal force; "M" is bending moment at the joint; "Axial" is vertical force (compression positive).
| Load case | Axial (kip) | Shear (kip) | Moment Mjoint (kip-ft) | Notes |
|---|---|---|---|---|
| LC1 — Transit: 5 kt, 15 kt wind, 3-ft seas | 9.2 ± 1.5 | 0.6 | ≈ 2 | Thrust ≈ 0.1 kip/leg at 12.5 ft below joint; tiny |
| LC2 — Parked on tethers: 25 kt, 6-ft seas | 12.4 ± 3 | 1.2 | ≈ 6 | Incl. 3.3 kip static tether tension |
| LC3 — Survival: 70 kt gusts, Hs 15 ft, on tethers | +19 / −10 | 4.1 | 60 (design) | Wind 9.4 kip on house ÷ 3 legs; wave dynamics; tether snap to ~10 kip; uplift case in troughs |
| LC4 — Accidental: collision/grounding, 40 kip at 3 ft below WL | — | 40 | ≈ 410 | Fuse bolts recommended (§6.4) |
| LC5 — Heave-plate slam (survival sea) | — | 12 (impulsive) | ≈ 66 into shell | Spread by internal ring girder; fatigue-governed |
Derivations: storm wind q = 0.00256 V² ≈ 24.6 psf × ~380 ft² of house/walkway area = 9.4 kip at ≈ +11 ft → heel moment 103 kip-ft, reacted as vertical couples at the legs (only ±2.9 kip of buoyancy shift — trivial) and horizontal shear of 3.1 kip per leg. Wave horizontal load per leg (Morison, Hs 15 ft, T = 10 s, beam-sea projected width ≈ 1.8 ft avg) ≈ 0.9–1.0 kip with centroid ≈ 10.9 ft below the joint. Spanning buoyancy imbalance between legs in a 15-ft sea is bounded quasi-statically at ~500 kip-ft of hull-girder moment but the platform largely follows waves of this period; §7 uses a design value of 200–250 kip-ft.
A lever multiplies force into moment. Whether that moment is dangerous depends on the section modulus resisting it. Your legs are not slender tubes — they are 8.5-ft-chord airfoils. Even a thin skin on that shape is a monster beam.
| Property | Athwartship bending (weak axis) | Fore-aft bending (strong axis) |
|---|---|---|
| Shell cross-sectional area | 0.30 ft² (43.8 in²) | |
| Moment of inertia I | 0.39 ft⁴ | ≈ 1.7 ft⁴ |
| Section modulus Z | 455 in³ | ≈ 690 in³ |
| Case | M (kip-ft) | σ (psi) | Utilization vs 30 ksi |
|---|---|---|---|
| LC3 survival design moment | 60 | 1,580 | 5% |
| Hull-girder-scale hypothetical (250 kip-ft) | 250 | 6,600 | 22% |
| LC4 collision, no fuse | 410 | 10,800 | 36% |
Hydrostatic check: 3.2 psi at 7.25 ft draft requires frame spacing ≈ 12 in at 3/16 in skin, or ≈ 8 in at 1/8 in — normal shipyard practice, already reflected in the mass budget.
| Action (ultimate, LC3/LC4) | Demand | Capacity of proposed flange | Margin |
|---|---|---|---|
| Bending moment | 60 kip-ft (250 with fuse blown) | > 1,000 kip-ft slip capacity (ΣμT·r over bolt group) | > 15× |
| Horizontal shear | 4–40 kip | ≈ 20 bolts × 19 kip slip/bolt ≈ 380 kip | > 9× |
| Uplift (trough + rocking) | 10 kip | 20 bolts × ~38 kip proof → ≫ demand even with prying | > 20× |
| Compression | 19 kip | Bearing on 1¼ in plate — trivial | ≫ |
In practice the flange is sized not by static strength but by fatigue and slip-retention policy: enough clamp force that the faying interface never micro-slips under the ±5–15 kip wave-frequency cycling (≈ 3–5 million cycles/year). That is what drives 20–24 bolts rather than the 6 that static strength alone would need.
Because the leg shell survives a 410 kip-ft hit at only ~36% of yield, the thing you actually want to protect is the node and the frame. Make 4 of the 24 bolts undersized shear pins (or necked pins) calibrated to shear at ≈ 150 kip-ft of joint moment. Below that threshold the joint is untouched; above it, the pins sacrifice themselves, the leg bends (repairable), and the node stays true. Pins are replaced with hand tools in an hour.
Without cables, the triangle becomes a self-supporting space box girder: floor + ceiling as flanges, the three walls as webs. Your planned inner triangle (22 ft sides, beams at wall midpoints, floor and ceiling) is exactly the right move — it halves every remaining span.
| Effect | Design value | Driver |
|---|---|---|
| Hull-girder bending moment | 200–250 kip-ft | Waves of 3–5 s period that the platform cannot follow (quasi-static bound 500 kip-ft is overly conservative for long swells it does follow) |
| Flange (chord) force T = M / 7 ft | ≈ 30–36 kip | Taken by wall top & bottom rails |
| Vertical corner reactions | +20 / −10 kip | Buoyancy redistribution, tether snap |
| Torsion (differential thrust, wind eccentricity) | ≈ 15 kip-ft | Closed triangular cell — very stiff, easy |
| Corner node moment | 150 kip-ft working / 250 kip-ft ultimate | LC3 + spanning + slam coherence |
| Member | Suggested section | Peak stress | Comment |
|---|---|---|---|
| Wall top & bottom rails (3 each level) — the hull-girder chords | RHS 6×6×3/8 | ≈ 10 ksi | Also picks up walkway brackets and railing loads |
| Inner triangle beams, floor & ceiling (22 ft spans) | RHS 8×4×5/16 | ≈ 7 ksi | w ≈ 150 lb/ft → M ≈ 9.1 kip-ft |
| Floor / ceiling joists (≤ 11 ft spans after subdivision) | RHS 4×2×3/16 @ 24 in | ≈ 7 ksi | 100 psf live + 15 psf dead |
| Wall studs @ 24 in | RHS 3×3×3/16 | < 3 ksi | Storm wind 17.5 psf is trivial; size for handling & slam |
| Corner nodes (3) | Machined 1¼ in plate cluster or 2205 casting | design to 250 kip-ft | The critical fabricated items. Full-pen welds, ground toes, MPI-inspected, done at the Chinese yard under controlled conditions |
| Walkway brackets & diagonals | 6061-Al 2×2×1/8, isolated from duplex | — | Nylon/isolation washers to prevent galvanic action |
| Mode | Free-floating | On tension legs | Comment |
|---|---|---|---|
| Heave | ≈ 3.2 s | ≈ 1.3 s | Free-floating heave sits near 3–4 s wind-chop energy → expect noticeable bobbing in fresh chop; tethers move you clear of it entirely. Heave plates add mass & damping — helpful. |
| Roll / pitch | ≈ 2.3 s | unchanged | Very stiff (GM ≈ 39 ft from the wide stance). Quick but small angles; the "soft ride" comes from low angular excitation, not slow periods. |
This is informational for the ride-quality discussion — it does not change the joint conclusion. If anything, tethered operation (short periods, low amplitudes) is the easiest case for the bolted joints.
| Criterion | No cables (bolted) | With cables |
|---|---|---|
| Strength adequacy | ✔ Fully adequate (§5–7) | ✔ Adequate, with added redundancy |
| Corner stiffness / micro-motion | Good | Slightly better — cables damp node micro-rotation |
| Drag — hydrodynamic | ✔ Clean | ≈ Equal if cables attach above the waterline; real penalty only if attached below WL for better moment arms |
| Drag — aerodynamic | ✔ Clean | ~190 lb extra in 70 kt gusts (negligible vs 9,400 lb house load) |
| Maintenance | ✔ None beyond normal inspection | Annual tension checks, fitting inspection; rod/wire replacement at yr 10–15 |
| Noise/vibration | ✔ None (minor shell drumming at waterline — damped by heave-plate isolation) | Aeolian strum on rods in 15+ kt winds unless fitted with dampers/spirals |
| Assembly simplicity | ✔ One bolt-up operation | Two operations + rigging tensioning sequence |
| Damage tolerance | Good (fuse bolts) | Very good (cables arrest a cracked-node scenario) |
| Shipping (your 45-ft HC constraint) | ✔ Nothing extra | Reels/boxes of rod, turnbuckles, lugs — modest but real cube |
| Item | Rod-rigging version | Wire-rope version |
|---|---|---|
| 6 rigging members (≈ 25 ft each) + turnbuckles + terminals | +950 lb | +520 lb |
| Hard-point lugs on legs & frame (12) | +280 lb | +280 lb |
| Frame/node lightening enabled by cables | −850 lb | −850 lb |
| Net delta vs. no-cable | +380 lb (+1.4% Δ) | −50 lb (wash) |
Weight is a wash — less than ±1.5% of displacement either way. It should not drive the decision.
| Item | Rod-rigging version | Wire-rope version |
|---|---|---|
| Rigging supply & install | +$8–14k | +$3–6k |
| Hard-point machining/welding | +$1.5–2.5k | +$1.5–2.5k |
| Node/frame simplification credit | −$2–4k | −$2–4k |
| Capex delta | +$7–12k | +$2–4k |
| O&M delta (inspections, retensioning) | +$0.8–1.5k/yr | +$0.5–1k/yr |
| Replacement at yr 10–15 | $6–12k | $3–6k |